Using pull and flow systems to improve production stability in real estate development projects

Dupin, P., 2021. Using pull and flow systems to improve production stability in real estate development projects. PhD, Nottingham Trent University.

[img]
Preview
Text
Patrick DUPIN PhD thesis.pdf - Published version

Download (14MB) | Preview

Abstract

Objectives: The objective of this thesis is to understand the effects of the application of flow-based management systems on medium-size sites (€2-50 million work turnover) made by medium-sized companies (20-200 employees). The purpose of this research is to develop and evaluate a pull scheduling system based on the Last Planner™ System (LPS) to improve production flow stability of real estate developments made by SMEs. The research investigates the application of pull systems from manufacturing industries and those that have not been fully tested in the construction industry.

Method: A three-block real estate development project in Brussels was used to ground the context where action research was chosen to initiate the research. Action research follows an ascending spiral that consists of 4 phases described in 1991 by Zuber-Skerrit: 1) planning, 2) acting, 3) observing and 4) reflecting. Once the first circle is initiated, the four activities lead to the next cycle. The reflections phase of circle (n) then leads to the planning phase of circle (n+1). These loops can be derived indefinitely or at least while the research has not met its objectives. Passing from action to critical reflection and back and vice versa in a cyclical process helps build a wider view and a greater understanding. In this context, three action circles were conducted. In this way, the methods, data and interpretation were continuously refined (Dick, 2002). The sequential development of the three blocks made by the same teams eased the process of capturing insights from a phase and building an optimal scheduling process. A lack of works planning, and progress understanding was found to be a major issue when the research started on the ongoing works of the first block. 5S and LPS were tested as a means of improving construction works planning at both the physical and managerial levels. The application of the first three Ss (sort, set, shine) yielded an impact on respect for the work site but were not sufficient to significantly affect the planning. The application of the first two steps of the LPS (master planning, phase planning and make ready) showed improvement but were also limited in their impact in the search for planning reliability. On-site measurements showed that despite a high percentage plan completion (PPC) score in the LPS, analysis of the progress of each apartment showed high volatility from one 23 / 408 week to the next. This volatility came from a lack of visibility in the scheduling system. Although the progress of each week was determined by what was and should have been done based on the LPS, more structure in the scheduling system and more reliability in the forecasts of the works were needed to increase the works stability. Given that takt time has been successfully used in the manufacturing industry to address variability in the demand, and that significant similarities exist between a construction site and a manufacturing line, it was decided to test this as a complement to the LPS in the research action taken on the second block of the building development. Encouraging results were measured, and on-site work in this block was improved.

Findings: it was found that the discipline needed to respect the system, the rules and sequence of the work demanded high-level and constant surveillance from site management. In the long run, this could put the whole system at risk. In order to be as efficient, sustainable and duplicable as possible, the scheduling system should be visual, need no interpretation and lead works in a pull flow. Manufacturing has successfully used a simple but efficient system named kanban to achieve level production and ensure a fully pulled system in a variable demand environment while limiting the sources of errors. The third block proved that such a method can work in conjunction with takt time and LPS and improve the works stability by favouring a self-pull system.

Impact: following the scheduling system developed by the action circles in Block 2, there has been a reduction of nearly 20% of the lead time measured and a significant increase in quality (the number of snagging works decreased by 95%). Therefore, the stress on the site management team decreased (captured by interviews). The early findings and encouraging results are signs of the importance of the research undertaken.

Limitations: The research has been conducted on traditional sites regarding typology, size, techniques, management structure, and contractors, so the findings are addressed to a wide audience across the construction industry. The limitation of the research comes from the domain of the construction observed: real estate in Belgium. Although it is highly probable that the issues detected on site by the research and the mechanisms used to address those issues are duplicable in other domains of the construction industry, there is, at this point of the research, no clear evidence.

Item Type: Thesis
Creators: Dupin, P.
Date: July 2021
Rights: You may copy up to 5% of this work for private study, or personal, non-commercial research. Any re-use of the information contained within this document should be fully referenced, quoting the author, title, university, degree level and pagination. Queries or requests for any other use, or if a more substantial copy is required, should be directed in the owner of the Intellectual Property Rights.
Divisions: Schools > School of Architecture, Design and the Built Environment
Record created by: Jeremy Silvester
Date Added: 13 Aug 2021 08:31
Last Modified: 13 Aug 2021 08:31
URI: https://irep.ntu.ac.uk/id/eprint/43929

Actions (login required)

Edit View Edit View

Views

Views per month over past year

Downloads

Downloads per month over past year